Upcoming work on the Jim Soorley Bikeway 10th to 23rd July 2023

Works are planned for the construction of the Cannery Creek – New Sewer Project’s Wetland & Bio-Retention Basin.

Night #1 (tentatively between 10th to 23rd July 2023)

  • saw Cut bikeway crossing
  • excavate/box out 5m wide 350mm deep below existing bikeway
  • compact ground and Engineering fill
  • install and level precast slab
  • chamfer the level difference between
  • install slow warning for cyclist

 

Night #2 (tentatively between 10th to 23rd July 2023)

  • reinstate asphalt work
  • install boom gates, concrete barrier

 